PV Grid Connection – Montalto di Castro

PV Grid Connection – Montalto di Castro

CEBAT supports Enfinity Global for connectivity infrastructure.

CEBAT supported the development of photovoltaic projects in the Montalto di Castro area, overseeing the design and construction of electrical grid connection infrastructure. The project involved medium voltage works with particular attention to integration with existing infrastructure.

Activities included:

  • Executive design of medium voltage cable ducts, with 630 mm² cables, even in complex configurations shared between different developers within the same trenches
  • Installation and testing of cable ducts and ancillary infrastructure, including excavation, cable laying and civil works
  • Coordination of construction site activities, in compliance with technical and authorization requirements.

The project contributes to the development of renewable energy capacity and the energy transition of the area.